10 steps to a green and more efficient production

Carbon reduction for green production - all you need to know
10 steps to green compressed air production

Everything you need to know about your pneumatic conveying process

Discover how you can create a more efficient pneumatic conveying process.
3D images of blowers in cement plant
Close
Industrial grey landscape environmental pollution waste of cement factory. Big pipes of industry enterprise plant. mountains of sand and rubble

AIRScan helps leading cement manufacturer cut CO2 emissions

In this case study we cover how the country's foremost manufacturer of cement were able to cut their carbon emissions and save 1,20,356 kWh of energy per year.

We partnered with a major cement manufacturer in Karnataka to assess their compressed air management system, and to identify the savings potential though realistic and simple actions. They had two compressed air networks (mainly for conveying and instrument air), comprising of 31 compressors in total with different capacities and for varying applications.

Project overview

With initial discussion, our Energy Consultancy team conducted one complimentary walkthrough audit and identified the pathway for optimization. Both parties discussed the proposals and concluded that measurement was necessary before any action.

The AIRScan compressed air audit was conducted at customer premises vy our compressed air experts. Site information was compiled in a comprehensive AIRScan report for an action plan that would result in tangible savings.

 

The implementation of simple leak arresting with proper planning and strategy, helped the utility team observe savings of 1,20,356 kWh per year, resulting in utility cost savings amounting to INR 9 lakh.

The customer

The customer is India's foremost manufacturer of cement and ready mixed concrete with a countrywide network. In 2021, it became the first and only Indian cement company to sign the Net Zero pledge. Their carbon emission reduction targets for 2030 were validated by the Science Based Targets Initiative (SBTi). 

Location

Wadi, Karnataka

The challenge

A broadly spread compressed air network and tough barrier for the team of auditors while performing the audit activities. However unstinting support from the the customer's utility team and a good understanding of compressed air system, helped us complete the activity within 20-30.

Assessment

AirScan infographics

Generation side

Out of the 31 total compressors, approx. 18 compressors are running with maximum loading. Key findings included like maintenance planning, overhauling of schedule, upgradation analysis, central controller feasibility, dryer uptime, room ventilation. 

 

Distribution side

While 2 different networks, no major pressure drops were observed except in coal mill, kiln and fly ash purging header. Key findings included pipeline layout, choked pipe replacements.

 

 

 

Demand side

With multiple flow-pressure meters and different areas of consumption, non-productive usages were identified with key findings like requirement and artificial demand.

 

 

 

Solutions and recommendations

case study solutions

Recommendations were provided keeping practicality and feasibility in mind in relation to the outcome benefits. These were categorized in priorities for better action planning.

Implementation & outcome

energy consumption scenario

The customer's utility team took the recommendations on very serious note and acted on the leak repair activity first as this was very easy to implement with the AIRScan report (coloured image/are-description) and the investment part it not required. With sincere efforts, within 30-45 days of time all the identified leakages were rectified. After the rectification activity, Atlas Copco team once again visited the site and captured the site running data in accordance with the production output for the validations.

 

Energy savings of 2553 kWh/week (120356 kWh & 9 lakh per year) were realized through the AIRScan recommendation implementation in Instrument air network and the same was verified though the installed energy meters and compressor running counters/utilization. Also, customer is in process of upgrading their conveying system to the Industrial highly efficient blower and expecting savings of 130000 kWh per year.

 

Ashish PJ, Audit Engineer: Handling such broad compressed air network project was really challenging but with the help of customer support and intention toward optimization scopes made the execution informative and engaging.

 

Yukesh Raj Deenan, Energy Consultant: Happy to contribute to the client’s net zero initiative and overwhelmed to be part of such result centric project.

Summing up

As there are many aspects to energy optimization in compressed air network, it is important to have holistic view of the existing condition and the client’s future needs. Even small, simple steps can contribute significantly. The saying “If you can’t measure, you can’t improve” really goes well with the compressed air system management.

Know more about the technology featured in this story

contact icon